Step by step - 2009

Railroading - 2nd stage

We started with extension our yard in the spring 2009. Is concerned about extension of the line from station Orechov concretely. It will double line, because single line has certain trammels.
We used a flexible track from the Thiel company. These track offer more facilities for shaping of the line. Montage of the flexible track is more laborious, but the final result is better.

Field of sleepers in two variants.

Slipping of the rails.

Drilling jig ...

... into which the rail string
a needle ...

... and we drill two plain holes.

Prebored holes.

Traction bond.

Connected rails.

Modelling tracked connection.

Traction bond on RhB.

Traction bond on RhB.

Triangulation of the new line.

Deeping of ballast.

Ballast laying.

Ballast laying.

I set ends of the rails before roll
bending by LEBU bonds. Rails
are moving during roll bending.

Roll bending of the track field.

Detail of the bending machine
with a measure.

Roll bending of the
first curve.

The first curve is bent.

The first section of double line.

The first section of double line.

Preparing of the next section.

Deeping of ballast.

The line in curve in front
of garden-plot.

The line in curve in front
of garden-plot.

Straight section towards
Orechov.

Straight section in the direction
from Orechov.

Triangulation of the
line along fence.

Deeping of ballast.

Straight section.

Deeping of ballast for
next section.

Tracks lying.

Gridiron triangulation of the new
station Moravany.

Deeping of ballast for new
gridiron.

Deeping of ballast for new
gridiron.

Assembling of switches.

The new gridiron is partially lied.

The new gridiron is partially lied.

Station tracks are partially lied.

Station tracks are partially lied.

Straight section of the new
double line.


Up

We continued to building a new station Moravany during summer vacation. We have to lay down six full composts storage bins, therefore we delayed. We perspired some liters at first and then we could lay all station tracks and the second gridiron. Shunting lines and depot have left yet.

Tracks and switches lying.

Tracks and switches lying and
triangulation.

Tracks and switches lying and
triangulation.

Station tracks.

Right station gridiron with slight
switches turns out well.

View on the station tracks from
the right gridiron.

Left gridiron is not completed
yet.

Switches on the right gridiron
were completed for train
crossing.

Two turn-out tracks were
completed.

View on the left gridiron.

General view on the station
Moravany.

View on station tracks from left
gridiron.


Up


We continue with building of track for store-house. New engine shed is nascent, too. Supply of switches from Thiel company is delayed, unfortunately. The reason is economic recession. Subcontractor of cast frogs became bankrupt and company Thiel had to look for other subcontractor. Switches producing continued at this time, but we are waiting for another switches. That is way we will continue in the spring, I think.

I used Y switch for trap sidings.

Trap sidings of future
store-house.

Track lyings for new engine shed.

Triangulation of distance
between tracks by location
of scheduled buildings.

Tracks are partially lied.

Tracks are partially lied.

General view on the left gridiron
under construction.


Up


Bridge No. 2 rebuilding

We plan reconstructions of bridges No. 2 (Javornik´s bridge) and No. 1 (Vresovice´s bridge) this year. Bridge No. 2 has been reconstructed as the first. Its butress walls warped heavily and its rail track deck has been mounted as provisional in 2006 year. The line is in deep incision and we decided to make a tunnel in the end. The local line will crossing main line above one of tunnel portal in natural terrain. Company ASYmodel implemented these rebuildings.

Original condition of the bridge.

Original condition of the bridge.

Right side of the tunnel before
compilation.

Sandstone packets for tunnel
anchoring.

Fixation of portals and left side.

Fixation of portals and left side.

Caking of glued-on parts.

Mr Chudoba adjustments joints
of the right side.

Settlement of the right side.

Examination of passability by
the express car.

Local line routing above the
tunnel.

Tunnel tube is not close yet.

Northern tunnel portal.

Southern tunnel portal.

Top foil against root penetration.

Stepping sandstone and
concrete packets.

Southern portal is imbedded into
surrounding terrain.

Southern portal is imbedded into
surrounding terrain.

Northern portal is imbedded into
surrounding terrain.

View into tunnel.

General view to the tunnel and
local line.

General view to the tunnel.


Up


Bridge No. 1 rebuilding

Bridge No. 1 was rebuild with bridge No. 2 together. We planned to replace only rail track deck. But original concrete blocks were clear away finally. New sandstone bridge pillars were build. All section is lighter now.

Original condition of the bridge.

Provisionally built bridge.

Provisionally built bridge.

Provisionally built bridge.

Bridge pillars are riveted by stones.

View under the bridge towards
tunnel.

Local line over the bridge
towards Vresova.

Local line over the bridge
towards Smrk.

View on the rail track deck.

View on the bridge towards
Vresova.

General view on the bridge.


Up